News Detail

First Firing PLTU Kaltim 2 (2x100MW)

26 / 08 / 2019 - Press Release

     

PLTU Kaltim 2- East Kalimantan, which is one of the works of PT D&C Engineering Company, has carried out its first firing or blaming the first boiler on August 26, 2019.

The first phase of the 2x100 MW coal-fired power plant project can be completed in less than 2 years, and can be completed sooner than the set time target. The overall progress currently includes the work of Engineering Progress 100%, Procurement Progress 99.5% and Construction Progress 95%. Kaltim 2 PLTU is targeted to be fully operational by the end of November 2019.

The Kaltim2 power plant is a power plant in the eastern part of Kalimantan Island and is an embodiment of the participation of the China Chengda Corporation Corporation, which was carried out on Kalimantan Island.